Interlaken has been hired by the City of Oregon City to install approximately 800 lineal feet of 15″ & 10″ sanitary sewer main, including a 269 foot pipe burst. The project began at the end of September and is scheduled to conclude in the middle of December. Progress has been on track and successful. Here are a few images of the pipe burst section we completed last week.